
AGENDA
ITEM BACKGROUND
|
TO: GOVERNING BOARD |
DATE April 7, 2007 |
||
|
FROM: PRESIDENT |
|||
|
SUBJECT: Award
of Bid: Allied Health Complex |
|||
|
ENCLOSURE(S) Page
1 of 2 |
|||
|
REASON FOR BOARD CONSIDERATION ACTION
|
ITEM NUMBER 19. |
||
Background:
The site work and under ground utilities have
been completed for the Allied Health Complex.
The building plans were approved by DSA and the district received
approval from the State Chancellors’ Office to proceed to bid. The bid opening was scheduled for March 27,
2008.
The District received five bid proposals with
a spread of 5% between high and low bib.
The apparent low bidder was Solpac Construction dba: Soltek Construction
out of
FISCAL
IMPACT:
None at this time
RECOMMENDATION:
It is recommended that the Governing Board defer
award of a contract at this time, and that the Governing Board schedule a
separate meeting later in April to review the bid proposals for the Allied
Health Complex.