Building 300 Renovation Project

Project Manager-Paul Anderson (831) 479-5086

Project Coordinator-Susan Robinson (831) 479-5095

Project Architect is RMW Archticture & Interiors - Steve Stenton (408) 294-8000

This project is for reconstruction of Building 300.  The project will renovate 12,523 square feet of the former Visual Arts Building.  This space will house classrooms and office administration.

The Mandatory Job Walk was conducted on December 1, 2009 with 50 contractors!

Bids were opened on January 12, 2010.  Please click the link on the left to see the complete bid results which includes, All contractors, Amounts Bid and all subcontractors stated.  Board Approval  was obtained at the meeting that was held on February 1, 2010. 

Tombleson Incorporated was awarded the contract and is expected to complete

the project in November 2010.

 

 

 

 

 

 

 

 

 

 

 